Tennessee Releases Renderings of Neyland Stadium Renovations

258 A8971 Headshot

After the University of Tennessee Board of Trustees approved a $49 million budget increase for the first phase of the Neyland Stadium renovation, the school this week released renderings of the $337 million project. Here's a look at what the school envisions, as well as a timeline for each phase of the project: 

Fall 2023

  • Removal of South Stadium Hall with structural strengthening of the stadium's south end
  • Partially completed Wi-Fi capabilities
  • Brick cladding around in-bowl vomitories
  • New restrooms under the Gate 10 ramp

Fall 2024

  • Full stadium-wide Wi-Fi connectivity
  • Stadium kitchen, commissary and loading dock
  • New southeast elevators vertically connecting all concourses
  • New Gate 4 entry plaza
  • Brick cladding around in-bowl vomitories (phase 2)
  • Renovations and upgrades complete for all stadium skyboxes (see updated renderings below) 
  • Initial construction for the westside Founders Suites New restrooms and concessions on north concourse two 

Fall 2025

  • Expanded south concourse 1 (increased restrooms, enhanced concessions, wider concourse)
  • Completed Founders Suites
  • Tee Martin Drive to shift south of the Gate 10 ramp

Fall 2026

  • Completion of entry plazas


Page 1 of 215
Next Page
Buyer's Guide
Information on more than 3,000 companies, sorted by category. Listings are updated daily.
Learn More
Buyer's Guide
AB Show 2025 in San Diego
AB Show is a solution-focused event for athletics, fitness, recreation and military professionals.
Nov. 5-8, 2025
Learn More
AB Show 2025