It took two and a half years and slightly more than a billion dollars to build U.S. Bank Stadium. Four years later, it's going to take two years and another $21 million to fix it.

Persistent leaks exacerbated  by wind and snow loads have forced the Minnesota Sports Facilities Authority to replace the entire facade.

“All parties agreed it was in the MSFA’s best interest to replace the original exterior enclosure with a superior system to what is currently in place.” MFSA and Mortenson Construction said in a joint statement.