The University of Minnesota's TCF Bank Stadium will undergo $6.6 million in renovations to meet the needs of the Minnesota Vikings, under a plan presented this week to the Board of Regents.

The changes - including a new heating system for the playing field - will be billed to the Vikings, which will play the next two seasons at the U while the team's own new stadium is being built on the site of the Metrodome.

The Vikings' spokesman, Jeff Anderson, said Wednesday that the money will come from the $975 million Vikings stadium budget, which is funded by public and private dollars.

The changes are needed to adapt the Gophers' stadium, which was designed for the fall college football season, to operate into December and "possibly" January, and meet the requirements of the National Football League, according to the university. Parts of the 50,805-seat stadium, which opened in 2009, will have to be winterized to protect systems from freezing and damage, officials say.

The plan calls for the installation of a "field heating system," as well as replacing artificial turf and adding camera platforms, storage space and temporary bleachers for 1,750 fans.

Part of stadium budget

In May, the university agreed to make the upgrades as part of its lease agreement with the Vikings, which will pay up to $3 million a year to play at TCF Bank Stadium.

At the time, the two organizations issued a news release, saying that "the Vikings will reimburse the university for any required TCF Bank Stadium capital improvements."

However, the costs of relocating the team to its temporary home and the TCF upgrades were built into the original budget for the new Vikings stadium, said Michele Kelm-Helgen, chairwoman of the Metropolitan Sports Facilities Authority. The budget allotted $16 million for improvements and operating costs at TCF Stadium.

Last year, the regents authorized $3.5 million in stadium upgrades, plus an undetermined amount for the new heating system.

The final plan, which puts the total price tag at $6,641,000, is expected to be approved by the regents on Friday. The construction is slated to begin this month and finish by July. The contractor, Mortenson Construction of Golden Valley, is the same firm that built TCF Stadium and is building the new Vikings stadium on the site of the Metrodome.

Staff writer Mike Kaszuba contributed to this report. Maura Lerner · 612-673-7384

U STADIUM UPGRADES

The University of Minnesota Board of Regents is expected to vote Friday on a $6.6 million upgrade to TCF Bank Stadium to host the Vikings.

The planned changes:

·Install field-heating system

·Replace artificial turf

·Winterize spaces throughout the stadium

·Expand storage space

·Build additional camera platforms

·Add temporary bleachers for 1,750 fans

Cost: $6,6441,000.

Start construction: February

End construction: July

Source: University of Minnesota Board of Regents

 

February 13, 2014

 

 
Copyright © 2014 LexisNexis, a division of Reed Elsevier Inc. All Rights Reserved.
Terms and Conditions Privacy Policy
Page 1 of 208
Next Page
AB Show 2024 in New Orleans
AB Show is a solution-focused event for athletics, fitness, recreation and military professionals.
Nov. 19-22, 2024
Learn More
AB Show 2024
Buyer's Guide
Information on more than 3,000 companies, sorted by category. Listings are updated daily.
Learn More
Buyer's Guide